Water Main Replacement

White Oaks, Indigo Park, Jamestown Farms and Canterbury Hills Water Main Replacement


Scope of Work

As part JCSA’s renewal and replacement program, JCSA will be replacing approximately 22,000 feet of existing water mains. The project will also include the replacement and addition of fire hydrants and the replacement of JCSA owned water service lines. The project is being completed to replace aging infrastructure, provide increased service reliability and improve flow available for fire protection purposes in this area. The new water mains will be installed within the existing right-of-ways and easements. The project will be completed in phases to minimize impacts to residents.

Schedule

  • Begin Design and Permitting – April 2019
  • Complete Design and Permitting – April 2020
  • Bidding – May 2020
  • Begin Construction – September 2020
  • Complete Construction – September 2021

Budget

  • Estimated Budget – $3,300,000
  • Engineering Design and Permitting Contract (RK&K Engineers) – $412,565
  • Construction Contract - TBD

Milestones

  • Contract for Design and Permitting, Board of Directors Approval – March 2019

Next Steps

  • Complete field work including topographic survey, geotechnical investigation and environmental assessment.
  • JCSA crews to upgrade obsolete meter boxes.
  • Public meeting to be conducted after 30% design is completed.

Project Contact